PENG Jiankang, DONG Ruikun, YOU Hong. Mechanism on Hot Mix Asphalt Construction under Low Temperature Condition[J]. Journal of Civil and Environmental Engineering, 2009, 31(4): 66-69.
DOI:
PENG Jiankang, DONG Ruikun, YOU Hong. Mechanism on Hot Mix Asphalt Construction under Low Temperature Condition[J]. Journal of Civil and Environmental Engineering, 2009, 31(4): 66-69. DOI: 10.11835/j.issn.1674-4764.2009.04.013.
Mechanism on Hot Mix Asphalt Construction under Low Temperature Condition
In order to explore the mechanism of low temperature construction and influence of additives on the high temperature performance of the asphalt concrete pavement
the viscosity at 110 ℃
120 ℃ and 135 ℃ and softening point were measured for SBS modified asphalt and base asphalt with different additive content of ADZ
ADW or ADS
respectively. The additives can reduce viscosity of asphalt and realize construction of asphalt concrete in low temperature. The experimental results showed that: To some extent
three kinds of additives can reduce the viscosity of base asphalt or SBS modified bitumen. In contrast
at lower temperature (120 ℃or 110 ℃)
the viscosity of SBS modified asphalt and base asphalt with ADW or ADS were obvious smaller than that of ADZ. With the increase of the three types of additive content
the softening points of base asphalt also increased. However
the softening points of SBS modified asphalt with lower additive content of ADZ