Climb Height and Overflow of Grout in Shaft Base Grouting
Based on the assumptions of exponential fluid and narrow plate model
formulas for calculating the climb height of grout in shaft base post grouting was deduced. It is shown that the climb height of grout is mainly related to the grouting pressure
the shaft length
the shaft diameter and the mudcake thickness. With the theoretic analysis and case study
it is indicated that thicker mudcake
higher grouting pressure and shorter shaft length would lead to larger climb height and larger risk of overflow. The overflow of grout would be prevented by reducing the grouting pressure
the mudcake thickness and debris thickness. The overflow of grout can also be prevented by increasing the strength of mudcake. For the overflow shafts
intermission grouting would be employed. Compared with the ordinary shafts
the former has higher bearing capacity than the latter
resulting from the grout upwards along the shaft soil interface.