Approach to Effective Control on the Project Investment[J]. Journal of Civil and Environmental Engineering, 2002, 24(3). DOI: 10.11835/j.issn.1674-4764.2002.03.014.
in allusion to the three kinds of serious overvaluation (the budgetary estimate of project construction exceeds the rough estimate
the budget exceeds the budgetary estimate and the final accounts exceed the budget) causing uncontrollable project investment often appeared in domestic project construction
the main causes for that are analyzed. That is
the frequent project change and the malpractice of the cost managing system. In this paper
according to some real projects
the kinds and causes of project change are clarified and the malpractice of the cost managing system is analyzed. The effective approaches of reducing the project change
especially the united surveying and improving the cost managing system in order to make the effective control of the project investment are realized.